PINNACLE WEST CAPITAL CORP (PNW) FY 2021 MD&A

Verbatim Item 7 Management's Discussion and Analysis from PINNACLE WEST CAPITAL CORP's 10-K for fiscal year 2021. Filing date: 2022-02-25. Report date: 2021-12-31. Accession: 0000764622-22-000014.

This page reproduces the company's own Item 7 MD&A text from the linked SEC filing. It is filer text, not grepcent analysis, scoring, or investment advice.

Extracted from Item 7 to the first post-MD&A boundary after HTML sanitization. Confidence: high.

Company profile: PNW · All MD&A years: index · Next year: FY 2022

ITEM 7.  MANAGEMENT’S DISCUSSION AND ANALYSIS

OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS

INTRODUCTION

The following discussion should be read in conjunction with Pinnacle West’s Consolidated Financial Statements and APS’s Consolidated Financial Statements and the related Notes that appear in Item 8 of this report. This discussion provides a comparison of the 2021 results with 2020 results. A comparison of the 2020 results with 2019 results can be found in the Annual Report on Form 10-K for the fiscal year ended December 31, 2020.  For information on factors that may cause our actual future results to differ from those we currently seek or anticipate, see “Forward-Looking Statements” at the front of this report and “Risk Factors” in Item 1A.

OVERVIEW

Business Overview

Pinnacle West is an investor-owned electric utility holding company based in Phoenix, Arizona with consolidated assets of about $22 billion. For over 130 years, Pinnacle West and our affiliates have provided energy and energy-related products to people and businesses throughout Arizona.

Pinnacle West derives essentially all of our revenues and earnings from our principal subsidiary, APS. APS is Arizona’s largest and longest-serving electric company that generates safe, affordable, and reliable electricity for approximately 1.3 million retail customers in 11 of Arizona’s 15 counties. APS is also the operator and co-owner of Palo Verde — a primary source of electricity for the southwest United States and the largest nuclear power plant in the United States.

COVID-19 Pandemic

The COVID-19 pandemic continues to be an evolving situation. The Company is operating under long-standing pandemic and business continuity plans that exist to address situations including pandemics like COVID-19. We are focused on ensuring the health and safety of our employees, contractors, and the general public by helping limit the spread of this virus and ensuring continued, safe, and reliable electric service for APS customers.

We identified business-critical positions in our operations and support organizations, with backup personnel ready to assist if an issue arose. Additionally, efforts to ensure the health and safety of our employees resulted in bifurcated control rooms, thus reducing the number of employees in mission-critical locations. We also established COVID-19 safety protocols, social distancing practices and offering virtual options whenever possible. The Company also took rapid action to implement an all Company COVID-19 hotline, a focused COVID-19 team, and procured on-site COVID-19 testing at key facilities early in the pandemic. Through this testing, case management and contact tracing, the Company has been able to significantly limit COVID-19 transmission in the workplace. As a result of these efforts, we were able to maintain the continuity of the essential services that we provide to our customers, while also managing the spread of the virus and promoting the health, physical and mental well-being and safety of our employees, customers, and communities. In the summer of 2021, the Company began transitioning employees that were previously working remotely back to the workplace on a limited basis and began the reduction of our COVID-19 safety protocols and restrictions. Due to the COVID-19 variants and increased transmission

55

Table of Contents

rates, the Company has delayed its full transition back to the workplace and COVID-19 safety protocols and restrictions remain in place.

Essential planned work and capital investments are continuing during the pandemic with priority given to support fire mitigation and summer storm efforts, as well as heat related outages. Raw material shortages, rising inflation, COVID-19 related work force disruptions and natural disasters are putting increased pressure on the global supply chain. APS is experiencing some delays in finished materials and tight labor markets. To date, APS has not experienced labor or material supply chain shortages that have significantly impacted its ability to serve its customers’ needs. However, shortages are causing minor delays, and shifting of work projects based on material availability. If APS continues to experience delays in materials, it could experience an increase in purchased power costs for summer generation needs. Such increased purchased power costs would be expected to be recoverable through the PSA. See Note 4 for additional information on the PSA. APS has measures in place to continually monitor and evaluate resource needs and supply chain adequacy but cannot predict whether there will be material supply chain shortages in the future.

The Company’s operations and maintenance expenses, exclusive of bad debt expense, increased by approximately $4.3 million for the year ended December 31, 2021, primarily due to costs for personal protective equipment and other health and safety-related costs related to COVID-19.  We do not expect the Company’s operation and maintenance expenses to be materially impacted in 2022 by costs related to COVID-19.

While the total expected impact of COVID-19 on future sales is currently unknown, APS experienced higher electric residential sales and lower electric commercial and industrial sales from the outset of the pandemic through April 2021. Beginning in May 2021, electric sales from commercial and industrial customers increased to levels in line with pre-COVID-19 sales but residential sales continued to be higher than pre-COVID-19 sales. Based on past experience, a 1% variation in our annual residential and small commercial and industrial kWh sales projections under normal business conditions can result in increases or decreases in annual net income of approximately $20 million, and a 1% variation in our annual large commercial and industrial kWh sales projections under normal business conditions can result in increases or decreases in annual net income of approximately $5 million.

The Coronavirus Aid, Relief, and Economic Security (CARES) Act allows employers to defer payments of the employer share of Social Security payroll taxes that would have otherwise been owed from March 27, 2020, through December 31, 2020. We deferred the cash payment of the employer’s portion of Social Security payroll taxes for the period July 1, 2020, through December 31, 2020, which was approximately $18 million. We paid half of this cash deferral by December 31, 2021, and the remainder will be paid by December 31, 2022.

On June 30, 2020, FERC issued an order granting a waiver request related to the existing AFUDC rate calculation beginning March 1, 2020, through February 28, 2021. On February 23, 2021, this waiver was extended until September 30, 2021. On September 21, 2021, it was further extended until March 31, 2022. The order provides a simplified approach that companies may elect to implement in order to minimize the significant distorted effect on the AFUDC formula resulting from increased short-term debt financing during the COVID-19 pandemic. APS has adopted this simplified approach to computing the AFUDC composite rate by using a simple average of the actual historical short-term debt balances for 2019, instead of current period short-term debt balances, and has left all other aspects of the AFUDC formula composite rate calculation unchanged. This change impacts the AFUDC composite rate in both 2020 and 2021 but does not impact prior years. Furthermore, the change in the composite rate calculation

56

Table of Contents

does not impact our accounting treatment for these costs. The change did not have a material impact on our financial statements. See Note 1.

Due to COVID-19, APS voluntarily suspended disconnections of customers for nonpayment beginning March 13, 2020, until December 31, 2020. The suspension of disconnection of customers for nonpayment ended on January 1, 2021, and customers were automatically placed on eight-month payment arrangements if they had past due balances at the end of the disconnection period of $75 or greater. APS voluntarily began waiving late payment fees of its customers on March 13, 2020, and is continuing to waive late payment fees. APS has experienced and is continuing to experience an increase in bad debt expense associated with the COVID-19 pandemic, the Summer Disconnection Moratorium, and the related write-offs of customer delinquent accounts. See Note 4 for additional information regarding the Summer Disconnection Moratorium. The Summer Disconnection Moratorium, the suspension of disconnections due to COVID-19 and the increased bad debt expense associated with both events resulted in a negative impact to its 2021 operating results of approximately $25 million pre-tax above the impact of disconnections on its operating results for years that did not have the Summer Disconnection Moratorium or COVID-19. APS expects that the Summer Disconnection Moratorium, the suspension of disconnections due to COVID-19 and the increased bad debt expense associated with this will continue to negatively impact its operating results for the foreseeable future in amounts similar to 2020 and 2021. The estimated impact depends on certain current assumptions, including, but not limited to, customer behaviors, population, and employment growth.

In February 2021, due to COVID-19, APS delayed the annual reset of the PSA. Rather than the increase being effective February 2021, the PSA reset was implemented with 50% of the increase effective April 2021 and the remaining 50% increase effective November 2021. See Note 4.

More detailed discussion of the impacts and future uncertainties related to the COVID‑19 pandemic can be found throughout this Management’s Discussion and Analysis of Financial Condition and Results of Operations and the Combined Notes to Pinnacle West’s and APS’s financial statements that appear in Part II, Item 8 of this report and “Risk Factors” in Part I, Item 1A of this report.

Strategic Overview

Our strategy is to deliver shareholder value by creating a sustainable energy future for Arizona by serving our customers with clean, reliable, and affordable energy.

Clean Energy Commitment

We are committed to doing our part to make the future clean and carbon-free. As Arizona stewards, we do what is right for the people and prosperity of Arizona. Our vision is to create a sustainable energy future for Arizona through providing clean, affordable, and reliable energy. We can accomplish our visions through collaboration with customers, communities, employees, policymakers, shareholders, and other stakeholders. Our clean energy goal is based on sound science and supports continued growth and economic development while maintaining reliability and affordable prices for APS’s customers.

APS’s clean energy goals consist of three parts:

•A 2050 goal to provide 100% clean, carbon-free electricity;

•A 2030 target of achieving a resource mix that is 65% clean energy, with 45% of the generation portfolio coming from renewable energy; and

57

Table of Contents

•A commitment to end APS’s use of coal-fired generation by 2031.

APS’s ability to successfully execute its clean energy commitment is dependent upon a number of important external factors, some of which include a supportive regulatory environment, sales and customer growth, development of clean energy technologies and continued access to capital markets.

2050 Goal: 100% Clean, Carbon-Free Electricity. Achieving a fully clean, carbon-free energy mix by 2050 is our aspiration. The 2050 goal will involve new thinking and depends on improved and new technologies.

2030 Goal: 65% Clean Energy. APS has an energy mix that is already 50% clean with existing plans to add more renewables and energy storage before 2025. By building on those plans, APS intends to attain an energy mix that is 65% clean by 2030, with 45% of APS’s generation portfolio coming from renewable energy. “Clean” is measured as percent of energy mix which includes all carbon-free resources like nuclear and demand-side management, and “renewable” is expressed as a percent of retail sales. This target will serve as a checkpoint for our resource planning, investment strategy, and customer affordability efforts as APS moves toward 100% clean, carbon-free energy mix by 2050.

2031 Goal: End APS’s Use of Coal-Fired Generation. The commitment to end APS’s use of coal-fired generation by 2031 will require APS to cease use of coal-generation at Four Corners. APS has permanently retired more than 1,000 MW of coal-fired electric generating capacity. These closures and other measures taken by APS have resulted in a total reduction of carbon emissions of 33% since 2005. In addition, APS has committed to end the use of coal at its remaining Cholla units by 2025.

APS understands that the transition away from coal-fired power plants toward a clean energy future will pose unique economic challenges for the communities around these plants. We worked collaboratively with stakeholders and leaders of the Navajo Nation to consider the impacts of ceasing operation of APS coal-fired power plants on the communities surrounding those facilities to propose a comprehensive Coal Community Transition (“CCT”) plan. The proposed framework provided substantial financial and economic development support to build new economic opportunities and addresses a transition strategy for plant employees. We are committed to continuing our long-running partnership with the Navajo Nation in other areas as well, including expanding electrification and developing tribal renewable projects. Our proposed CCT plan supported the Navajo Nation, where Four Corners is located, the communities surrounding the Cholla Power Plant and the Hopi Tribe, which is impacted by closure of the Navajo Plant. On November 2, 2021, the ACC approved an amended 2019 Rate Case ROO that will require (i) equal payments over a three-year period that total $10 million to the Navajo Nation, (ii) a $1 million one-time payment to the Hopi Tribe within 60 days of the 2019 Rate Case decision, (iii) a $500,000 one-time payment to the Navajo County communities within 60 days of the 2019 Rate Case decision, (iv) up to $1.25 million for electrification of homes and businesses on the Hopi reservation and (v) up to $1.25 million for the electrification of homes and businesses on the Navajo Nation reservation. The payments and expenditures are attributable to the future closures of Four Corners and Cholla, along with the prior closure of the Navajo Plant. All ordered payments and expenditures would be recoverable through rates. See Note 4 for a discussion of the CCT plan.

In June 2021, APS and the owners of Four Corners entered into agreements to operate Four Corners seasonally beginning in fall 2023, subject to the necessary governmental approvals and conditions associated with changes in plant ownership. Under seasonal operation, a single unit will remain online year-round, subject to market conditions as well as planned maintenance outages and unplanned outages. In addition, the other unit will be operational throughout the summer season of June through October when

58

Table of Contents

customer demand is the highest. APS believes that operating Four Corners seasonally will bring environmental benefits and ensure continued service reliability for its customers, especially during Arizona’s hot summer months, as APS transitions to ceasing to use coal-fired generation by 2031. By moving to seasonal operations, Four Corners will become a more flexible resource that supports increasing amounts of clean energy, helping to compensate for the intermittent output of renewable resources. This change also helps ensure reliability of a critical energy source while reducing operations and maintenance costs. APS estimates that the shift to seasonal operations will reduce annual carbon emissions at Four Corners by an estimated 20-25%, as compared to current conditions.

Renewables. APS’s IRP (see Note 4 for additional information) establishes the path to meeting our clean energy commitment and maintaining reliable electric service for our customers. APS intends to strengthen its already diverse energy mix by increasing its investments in carbon-free resources. Our IRP rapidly adds clean energy and storage resources while maintaining reliable and affordable service. Its near-term actions are focused on clean energy and positive customer outcomes and includes: (a) competitive solicitations to procure clean energy resources such as solar, wind, energy storage, and DSM resources, all of which lead to a cleaner grid; and (b) strategic, short-term wholesale market purchases from a combination of existing merchant natural gas units, neighboring utility systems and wholesale market participants that ensure operational reliability.

APS has a diverse portfolio of existing and planned renewable resources, including solar, wind, geothermal, biomass and biogas that supports our commitment to clean energy, which is already strengthened by Palo Verde, the nation’s largest carbon-free, clean energy resource, that provides the foundation for reliable and affordable service for APS customers. APS’s longer-term clean energy strategy includes pursuing the right mix of purchased power contracts for new facilities, procurement of new facilities to be owned by APS, and the ongoing development of distributed energy resources. This balance will ensure an appropriately diverse portfolio designed to achieve the same operational reliability and customer affordability as APS’s near-term strategies. In addition, APS is actively seeking to include future facility purchase options in its PPAs that will enable investments with greater financial flexibility.

APS uses competitive “all source” requests for proposal (“RFPs”) to pursue market resources that meet its system needs and offer the best value for customers. APS selects projects based on cost and commercial viability, taking into consideration timing and likelihood of successful contracting and development. Under current market conditions, APS must aggressively contract for resources that can withstand supply chain and other geopolitical pressures. Available projects are guided by IRP timelines and quantities and APS maintains a flexible approach that allows it to optimize system reliability and customer affordability through the RFP process. Agreements for the development and completion of future resources are subject to various conditions, including successful siting, permitting and interconnection of the projects to the electric grid. See “Business of Arizona Public Service Company — Energy Sources and Resource Planning — Current and Future Resources — Renewable Energy Standard — Renewable Energy Portfolio” in Item 1 for details regarding APS’s renewable energy resources.

In September 2019, APS issued an RFP that requested up to 250 MW of wind resources to be in service as soon as possible, but no later than 2022. As a result of this RFP, APS executed a 200 MW PPA for a wind resource that went into service in January 2022. In December 2020, APS issued two additional RFPs: (i) a battery storage RFP for projects to be located at two AZ Sun sites; and (ii) an all source RFP that solicited resources to meet our clean energy needs and capacity to maintain system reliability, and was later amended to include a request for 150 MW of solar resources to be developed on APS property and owned by APS (collectively, the “December 2020 RFPs”). As a result of the all source RFP, APS executed a PPA in October 2021 for a 238 MW wind resource to be in service by June 2023, and also executed an

59

Table of Contents

engineering, procurement, and construction contract in November 2021 for a 150 MW solar resource to be owned by APS and in service in early 2023. APS continues to negotiate contracts for additional resources to be in service in 2024 in connection with the all source RFP. Once it secures those important resources and closes out the December 2020 RFPs, APS intends to issue its next all source RFP to address resource needs for 2025 and beyond.

Energy Storage. APS deploys a number of advanced technologies on its system, including energy storage. Energy storage provides capacity, improves power quality, can be utilized for system regulation and, in certain circumstances, be used to defer certain traditional infrastructure investments. Energy storage also aids in integrating renewable generation by storing excess energy when system demand is low and renewable production is high and then releasing the stored energy during peak demand hours later in the day and after sunset. APS is utilizing grid-scale energy storage projects to meet customer reliability requirements, increase renewable utilization, and to further our understanding of how storage works with other advanced technologies and the grid.

In 2018, APS issued an RFP for approximately 106 MW of energy storage to be located at up to five of its AZ Sun sites. Based upon its evaluation of the RFP responses, APS decided to expand the initial phase of battery deployment to 141 MW by adding a sixth AZ Sun site. These battery storage facilities are expected to be in service during the summer of 2022. On August 2, 2021, APS executed a contract for an additional 60 MW of utility-owned energy storage to be located on APS’s AZ Sun sites. This contract, with a 2023 in-service date, will complete the addition of storage on current APS-owned utility-scale solar facilities.

Additionally, in February 2019, APS signed two 20-year PPAs for energy storage totaling 150 MW. These PPAs were subject to ACC approval in order to allow for cost recovery through the PSA. APS received the requested ACC approval on January 12, 2021, and service under the agreements is expected to begin in 2022 with respect to 100 MW and in 2023 with respect to 50 MW.

As a result of its December 2020 RFPs, as of February 2022, APS has executed four 20-year PPAs for resources that include energy storage: (a) two PPAs for standalone energy storage resources totaling 300 MW; and (b) two PPAs totaling 275 MW solar plus storage resource. The PPAs are also subject to ACC approval to enable cost recovery through the PSA. APS received the requested ACC approval for three out of four of the projects on December 16, 2021. The remaining project was filed in February 2022 for ACC approval and is pending ACC review. Service under the agreements is expected to begin in 2023 and 2024.

APS currently plans to install more than 900 MW of energy storage by 2025, including the energy storage projects under PPAs and AZ Sun retrofits described above. The remaining energy storage is expected to be made up of resources solicited through current and future RFPs.

60

Table of Contents

The following table summarizes the resources in APS’s energy storage portfolio that are in operation and under development as of December 31, 2021. Agreements for the development and completion of future resources are subject to various conditions.

Net Capacity in Operation(MW)Net Capacity Planned / UnderDevelopment (MW)
APS Owned: Energy Storage201
PPAs - Energy Storage510
Residential Energy Storage12(a)3
Total Energy Storage Portfolio12714

(a)     This includes 11.7 MW of APS customer-owned batteries and 0.3 MW of APS-owned residential batteries.

Palo Verde. Palo Verde, the nation’s largest carbon-free, clean energy resource, will continue to be a foundational part of APS’s resource portfolio. The plant currently supplies nearly 70% of our clean energy and provides the foundation for the reliable and affordable service for APS customers. Palo Verde is not just the cornerstone of our current clean energy mix; it also is a significant provider of clean energy to the southwest United States. The plant is a critical asset to the Southwest, generating more than 32 million MWh annually – enough power for more than 4 million people. Its continued operation is important to a carbon-free and clean energy future for Arizona and the region, as a reliable, continuous, affordable resource and as a large contributor to the local economy.

Affordable

We believe it is APS’s responsibility to deliver electric services to customers in the most cost-effective manner. Since January 2018 through November 2021, the average residential bill decreased by 4.99%, or $7.48, due to net reductions in cost recovery adjustor mechanisms.

Building upon existing cost management efforts, APS launched a customer affordability initiative in 2019. The initiative was implemented company-wide to thoughtfully and deliberately assess our business processes and organizational approaches to completing high-value work and internal efficiencies. In 2021, APS continued to drive this initiative by identifying opportunities to streamline its business processes and deliver sustainable cost savings, which resulted in the Company identifying approximately $30 million in annual incremental cost saving opportunities in 2022.

Participation in the EIM continues to be a tool for creating savings for APS’s customers from the real-time, voluntary market. APS continues to expect that its participation in EIM will lower its fuel and purchased-power costs, improve situational awareness for system operations in the Western Interconnection power grid, and improve integration of APS’s renewable resources. APS continues to evaluate opportunities that benefit our customers and is exploring opportunities to move to a day-ahead market with the expectation of reliably achieving incrementally greater cost savings and using the region’s increasing renewable resources more efficiently. As part of that effort, APS is exploring several options. APS is in discussions with the current EIM operator, the CAISO, the Western Resource Adequacy Program, the Western Markets Exploratory Group, and the Southwest Power Pool. Each of these explorations also involve other entities and are being undertaken to evaluate the feasibility and cost/benefit of creating a voluntary day-ahead market.

61

Table of Contents

Reliable

While our energy mix evolves, the obligation to deliver reliable service to our customers remains. Notwithstanding the challenges presented by the COVID-19 pandemic, as well the Phoenix metropolitan experiencing the warmest June on record and its summer monsoon being the third wettest over the last 41 years, APS continued to provide reliable service to its customers in 2021.

Planned investments will support operating and maintaining the grid, updating technology, accommodating customer growth, and enabling more renewable energy resources. Our advanced distribution management system allows operators to locate outages, control line devices remotely and helps them coordinate more closely with field crews to safely maintain an increasingly dynamic grid. The system also integrates a new meter data management system that increases grid visibility and gives customers access to more of their energy usage data.

Wildfire safety remains a critical focus for APS and other utilities. We increased investment in fire mitigation efforts to clear defensible space around our infrastructure, build partnerships with government entities and first responders and educate customers and communities. These programs contribute to customer reliability, responsible forest management and safe communities.

The new units at our modernized Ocotillo Power Plant provide cleaner-running and more efficient units. They support reliability by responding quickly to the variability of solar generation and delivering energy in the late afternoon and early evening when solar production declines as the sun sets and customer demand peaks.

In April 2021, the CAISO sought FERC authorization for certain tariff changes intended to try to address risks associated with high heat weather events. Although APS is generally supportive of some of these changes, others would change the load, export, and wheeling priorities in a way that would unfairly benefit California entities at the expense of non-California entities. On June 25, 2021, FERC issued an order accepting the CAISO’s proposed changes. On July 26, 2021, APS filed seeking a rehearing of FERC’s June 25, 2021, order. On August 26, 2021, FERC issued a notice indicating that the pending requests for rehearing were denied by operation of law and providing for further consideration. The requests for rehearing will be addressed in a future FERC order. APS cannot predict the outcome of these proceedings.

APS’s key elements to delivering reliable power include resource planning, sufficient reserve margins, customer partnerships to manage peak demand, fire mitigation, and operational preparedness. Seasonal readiness procedures at APS also include walkdowns to ensure good material conditions and critical control system surveys. APS also plans for the unexpected by conducting emergency operations drills and coordinating on fire and emergency management with federal, state, and local agencies.

Customer-Focused

Recognizing that creating customer value is inextricably linked to increasing shareholder value, APS’s focus remains on its customers and the communities it serves. Accordingly, it is APS’s goal to achieve an industry-leading, best-in-class customer experience. This multi-year objective includes incrementally improving the company’s J.D. Power (“JDP”) overall customer satisfaction ratings from the fourth quartile to the first quartile of its peer set comprised of large investor-owned utilities. APS’s rating improved in 2021 with its fourth-quarter JDP residential overall customer satisfaction score ranked in the

62

Table of Contents

third quartile. APS made year-over-year improvements in power quality and reliability, billing and payment, and phone customer care.

In mid-2021, APS initiated an organization-wide customer experience strategy council designed to further drive a customer-oriented culture and improve JDP Company performance. Through this and other on-going customer-centric initiatives, APS has embraced increased empathy training for care center associates and adopted more flexible payment arrangements for customers. Numerous customer web-based enhancements also were implemented, including streamlined navigation and Spanish language transaction capabilities on aps.com; an enhanced online power outage center; and enrollment of more than 1 million customers for outage email and text notifications. Furthermore, APS launched a broad-reaching ad campaign focused on energy efficiency and financial assistance programs.

APS offers discounts to qualified limited-income customers, as well as programs to help customers stay current on their bills. Qualified customers experiencing an unplanned major expense or an unexpected reduction in income can receive up to $800 a year to cover current or past due APS bills through the Crisis Bill Assistance program. APS’s Energy Support program gives qualified limited-income customers a 25% discount on their bill each month. As of December 31, 2021, customers received almost $23 million in bill assistance from various sources, with the largest amount coming from the Arizona Department of Economic Security’s Emergency Rental Assistance Program. This combined funding will aid approximately 36,000 APS customers.

A customer advisory board and a consumer working group were formed in 2020, one made up of a cross-section of customers, and the other of stakeholders and advocates representing various customer interests, met several times in 2021 to keep APS apprised of customer needs, wants and perspectives. Their direct feedback helped facilitate improved analysis, education, and communication to customers about their rate plan options, rate names and related communications. As of December 1, 2021, about 54% of APS customers are on their most economical plan. The advisory board also helped inform an on-going redesign and enhancements to APS’s monthly bill based on additional customer feedback, research, and industry best practices.

Developing Clean Energy Technologies

Electric Vehicles

APS is making electric vehicle charging more accessible for its customers and helping Arizona businesses, schools and governments electrify their fleets. In 2021, APS continued its expansion of its Take Charge AZ Pilot Program. As of January 2022, APS had installed approximately 400 charging ports at business customer locations with more stations expected to be added through 2022. The program provides charging equipment, installation, and maintenance to business customers, government agencies, and multifamily housing communities. In addition to the Level 2 charging stations, APS has begun construction of DC fast charging stations that will be owned and operated by APS at five locations in Arizona. This project is projected to be completed during 2022, with each location including 2-150 kilowatt and 2-350 kilowatt DC fast charging stations. Charging at these stations will be accessible through the Electrify America charging network. APS also has a goal of 450,000 light-duty electric vehicles in its service territory by 2030.

Additionally, as part of the 2020 DSM Plan, the ACC approved programs for electric vehicles, including a residential program to measure electric vehicle charging as well as a $100 rebate to home builders for new home 240V charging station garage outlets.

63

Table of Contents

The ACC ordered the state’s public service corporations, including APS, to develop a long-term, comprehensive Statewide Transportation Electrification Plan (“TE Plan”) for Arizona. The TE Plan is intended to provide a roadmap for Transportation Electrification in Arizona, focused on realizing the associated air quality and economic development benefits for all residents in the state along with understanding the impact of electric vehicle charging on the grid. APS actively participated in developing this plan. The ACC approved the plan in December 2021. APS is currently working with stakeholders to develop a budget and implementation plan for ACC review.

Hydrogen Production

Palo Verde, in partnership with Idaho National Laboratory (“INL”), Energy Harbor Corporation (“Energy Harbor”) and Xcel Energy Incorporated (“Xcel”), was chosen by the DOE’s Office of Nuclear Energy to participate in a series of hydrogen production projects with the goal to improve the long-term economic competitiveness of the nuclear power industry. The multi-phase projects began in 2020 with a series of small-scale hydrogen production demonstration projects led by Energy Harbor and Xcel, as well as a technical and economic assessment performed by INL of using electricity generated at Palo Verde to produce hydrogen.

Based on the experience from Palo Verde’s utility partners’ small scale demonstration projects and from the Palo Verde-specific technical and economic assessment performed by INL, in April 2021, PNW Hydrogen LLC (“PNW Hydrogen”), a newly formed subsidiary of Pinnacle West, applied for DOE funding for a larger scale hydrogen production demonstration project using electricity sourced from Palo Verde. On October 7, 2021, PNW Hydrogen was notified that DOE’s Office of Energy Efficiency & Renewable Energy and Office of Nuclear Energy had selected PNW Hydrogen’s application for an award of $20 million in federal funding to support the hydrogen production demonstration project, subject to negotiation and execution of a definitive Cooperative Agreement funding instrument between PNW Hydrogen and DOE.

Carbon Capture

Carbon capture technologies can isolate CO2 and either sequester it permanently in geologic formations or convert it for use in products. Currently, almost all existing fossil fuel generators do not control carbon emissions the way they control emissions of other air pollutants such as sulfur dioxide or oxides of nitrogen. Carbon capture technologies are still in the demonstration phase and while they show promise, they are still being tested in real-world conditions. These technologies could offer the potential to keep in operation existing generators that otherwise would need to be retired. APS will continue to monitor this emerging technology.

Environmental, Social, and Governance (“ESG”) Practices

Pinnacle West has been integrating ESG practices into its core work for almost 30 years. As a business strategy, we seek solutions that provide “shared value,” meaning solutions that address societal and environmental challenges in a way that also delivers business value. Our commitment extends beyond implementing sustainability practices; we are dedicated to working with our stakeholders to identify and address the sustainability issues that we are uniquely positioned to impact through our business. In 2020, in support of our clean energy commitment and the growing focus on ESG within our organization, we increased our efforts by dedicating a new Sustainability Department at Pinnacle West to integrating ESG best practices into the everyday work of the Company.

64

Table of Contents

As a first step, the Company engaged the Electric Power Research Institute (“EPRI”) and leveraged input from employees, large customers, limited-income advocates, economic development groups, environmental non-governmental organizations, leading sustainability academics and other stakeholders to identify and assess the sustainability issues that matter most. In total, 23 Priority Sustainability Issues (“PSIs”) were identified and prioritized. The most critical category, Integral Shared Value, includes four issues deemed most important and most able to be impacted by our actions: clean energy, customer experience, energy access and reliability and safety and health. These Integral PSIs provide the foundation for informing our strategic direction, creating a framework for incorporating best practices and driving enterprise-wide alignment and accountability. In 2021, the Company engaged EPRI for the second phase of this work, focused on benchmarking best practices within these four Integral Shared Value PSIs. We will utilize the benchmarking information to identify opportunities for further improvement in our ESG performance.

In 2021, the Company established a Social Issues Committee Framework. The goal of the framework is to provide a process for considering emergent social issues, and for determining whether or how best to engage. The committee’s responsibility is to determine, using a set of principles grounded in the APS Promise and the PSIs, whether engagement on specific emergent social issues is appropriate and, if so, how best to engage.

In 2021, the Company finalized an ESG Strategic Framework to guide our work. The framework is based upon three foundational pillars: ESG Policy Advocacy (we advocate for policy that supports our clean energy goals); Driving Performance (improving our ESG performance in the most important areas, including our PSIs); and effectively communicating and amplifying our ESG story to our various stakeholders, including investors, customers, employees and beyond. The framework will guide and shape our ESG work moving forward.

Regulatory Overview

On October 31, 2019, APS filed an application with the ACC (the “2019 Rate Case”) seeking an increase in annual retail base rates of $69 million. This amount includes recovery of the deferral and rate base effects of the Four Corners selective catalytic reduction ("SCR") project that was the subject of a separate proceeding, see “Four Corners SCR Cost Recovery” in Note 4. It also reflects a net credit to base rates of approximately $115 million primarily due to the prospective inclusion of rate refunds currently provided through the TEAM. The proposed total annual revenue increase in APS’s application is $184 million. The average annual customer bill impact of APS’s request is an increase of 5.6% (the average annual bill impact for a typical APS residential customer is 5.4%).

The principal provisions of APS’s application were:

•a test year comprised of 12 months ended June 30, 2019, adjusted as described below;

•an original cost rate base of $8.87 billion, which approximates the ACC-jurisdictional portion of the book value of utility assets, net of accumulated depreciation and other credits;

•the following proposed capital structure and costs of capital:

Capital StructureCost of Capital
Long-term debt45.3%4.1%
Common stock equity54.7%10.15%
Weighted-average cost of capital7.41%

65

Table of Contents

•a 1% return on the increment of fair value rate base above APS’s original cost rate base, as provided for by Arizona law;

•a Base Fuel Rate of $0.030168 per kWh;

•authorization to defer until APS’s next general rate case the increase or decrease in its Arizona property taxes attributable to tax rate changes after the date the rate application is adjudicated;

•a number of proposed rate and program changes for residential customers, including:

▪a super off-peak period during the winter months for APS’s time-of-use with demand rates;

▪additional $1.25 million in funding for APS’s limited-income crisis bill program; and

▪a flat bill/subscription rate pilot program;

•proposed rate design changes for commercial customers, including an experimental program designed to provide access to market pricing for up to 200 MW of medium and large commercial customers;

•recovery of the deferral and rate base effects of the construction and operating costs of the Ocotillo modernization project. See Note 4 for a discussion of the 2017 Settlement Agreement; and

•continued recovery of the remaining investment and other costs related to the retirement and closure of the Navajo Plant. See Note 4 for details related to the resulting regulatory asset.

On October 2, 2020, the ACC Staff, the Residential Utility Consumer Office (“RUCO”) and other intervenors filed their initial written testimony with the ACC. The ACC Staff recommended, among other things, (i) a $89.7 million revenue increase, (ii) an average annual customer bill increase of 2.7%, (iii) a return on equity of 9.4%, (iv) a 0.3% or, as an alternative, a 0% return on the increment of fair value rate base greater than original cost, (v) the recovery of the deferral and rate base effects of the construction and operating costs of the Four Corners SCR project and (vi) the recovery of the rate base effects of the construction and ongoing consideration of the deferral of the Ocotillo modernization project. RUCO recommended, among other things, (i) a $20.8 million revenue decrease, (ii) an average annual customer bill decrease of 0.63%, (iii) a return on equity of 8.74%, (iv) a 0% return on the increment of fair value rate base, (v) the nonrecovery of the deferral and rate base effects of the construction and operating costs of the Four Corners SCR project pending further consideration, and (vi) the recovery of the deferral and rate base effects of the construction and operating costs of the Ocotillo modernization project.

The filed ACC Staff and intervenor testimony include additional recommendations, some of which materially differ from APS’s filed application. On November 6, 2020, APS filed its rebuttal testimony and the principal provisions which differ from its initial application include, among other things, a (i) $169 million revenue increase, (ii) average annual customer bill increase of 5.14%, (iii) return on equity of 10%, (iv) return on the increment of fair value rate base of 0.8%, (v) new cost recovery adjustor mechanism, the Advanced Energy Mechanism, to enable more timely recovery of clean investments as APS pursues its clean energy commitment, (vi) recognition that securitization is a potentially useful financing tool to recover the remaining book value of retiring assets and effectuate a transition to a cleaner energy future that APS intends to pursue, provided legislative hurdles are addressed, and (vii) the CCT plan related to the closure or future closure of coal-fired generation facilities of which $25 million would be funds that are not recoverable through rates with a proposal that the remainder be funded by customers over 10 years.

The CCT plan includes the following proposed components: (i) $100 million that will be paid over 10 years to the Navajo Nation for a sustainable transition to a post-coal economy, which would be funded by customers, (ii) $1.25 million that will be paid over five years to the Navajo Nation to fund an economic

66

Table of Contents

development organization, which would be funds not recoverable through rates, (iii) $10 million to facilitate electrification projects within the Navajo Nation, which would be funded equally by funds not recoverable through rates and by customers, (iv) $2.5 million per year in transmission revenue sharing to be paid to the Navajo Nation beginning after the closure of the Four Corners through 2038, which would be funds not recoverable through rates, (v) $12 million that will be paid over five years to the Navajo County Communities surrounding Cholla Power Plant, which would primarily be funded by customers, and (vi) $3.7 million that will be paid over five years to the Hopi Tribe related to APS’s ownership interests in the Navajo Plant, which would primarily be funded by customers. In 2021, APS committed an additional $900,000 to be paid to the Hopi Tribe related to APS’s ownership interests in the Navajo Plant.

On December 4, 2020, the ACC Staff and intervenors filed surrebuttal testimony. The ACC Staff reduced its recommended rate increase to $59.8 million, or an average annual customer bill increase of 1.82%. In RUCO’s surrebuttal, the recommended revenue decrease changed to $50.1 million, or an average annual customer bill decrease of 1.52%. The hearing concluded on March 3, 2021, and the post-hearing briefing concluded on April 30, 2021.

On August 2, 2021, the Administrative Law Judge issued a Recommended Opinion and Order in the 2019 Rate Case (the “2019 Rate Case ROO”) and issued corrections on September 10 and September 20, 2021. The 2019 Rate Case ROO recommended, among other things, (i) a $111 million decrease in annual revenue requirements, (ii) a return on equity of 9.16%, (iii) a 0.30% return on the increment of fair value rate base greater than original cost, with total fair value rate of return further adjusted to include a 0.03% reduction to return on equity resulting in an effective fair value rate of return of 4.95%, (iv) the nonrecovery of the deferral and rate base effects of the operating costs and construction of the Four Corners SCR project (see “Four Corners SCR Cost Recovery” below for additional information), (v) the recovery of the deferral and rate base effects of the operating costs and construction of the Ocotillo modernization project, which includes a reduction in the return on the deferral, (vi) a 15% disallowance of annual amortization of Navajo Plant regulatory asset recovery, (vii) the denial of the request to defer until APS’s next general rate case the increase or decrease in its Arizona property taxes attributable to tax rate changes, and (viii) a collaborative process to review and recommend revisions to APS’s adjustment mechanisms within 12 months after the date of the decision. The 2019 Rate Case ROO also recommended that the CCT plan include the following components: (i) $50 million that will be paid over 10 years to the Navajo Nation, (ii) $5 million that will be paid over five years to the Navajo County Communities surrounding Cholla Power Plant, and (iii) $1.675 million that will be paid to the Hopi Tribe related to APS’s ownership interests in the Navajo Plant. These amounts would be recoverable from APS’s customers through the RES adjustment mechanism. APS filed exceptions on September 13, 2021 regarding the disallowance of the SCR cost deferrals and plant investments that was recommended in the 2019 Rate Case ROO, among other issues.

On October 6, 2021 and October 27, 2021, the ACC voted on various amendments to the 2019 Rate Case ROO that would result in, among other things, (i) a return on equity of 8.70%, (ii) the recovery of the deferral and rate base effects of the operating costs and construction of the Four Corners SCR project, with the exception of $215.5 million (see “Four Corners SCR Cost Recovery” below), (iii) that the CCT plan include the following components: (a) a payment of $1 million to the Hopi Tribe within 60 days of the 2019 Rate Case decision, (b) a payment of $10 million over three years to the Navajo Nation, (c) a payment of $500,000 to the Navajo County communities within 60 days of the 2019 Rate Case decision, (d) up to $1.25 million for electrification of homes and businesses on the Hopi reservation and (e) up to $1.25 million for the electrification of homes and businesses on the Navajo Nation reservation. These payments and expenditures are attributable to the future closures of Four Corners and Cholla, along with the prior closure of the Navajo Plant and all ordered payments and expenditures would be recoverable

67

Table of Contents

through rates, and (iv) a change in the residential on-peak time-of-use period from 3 p.m. to 8 p.m. to 4 p.m. to 7p.m. Monday through Friday, excluding holidays. The 2019 Rate Case ROO, as amended, results in a total annual revenue decrease for APS of $4.8 million, excluding temporary CCT payments and expenditures. On November 2, 2021, the ACC approved the 2019 Rate Case ROO, as amended. On November 24, 2021, APS filed with the ACC an application for rehearing of the 2019 Rate Case and the application was deemed denied on December 15, 2021, as the ACC did not act upon it. On December 17, 2021, APS filed its Notice of Direct Appeal at the Arizona Court of Appeals and a Petition for Special Action with the Arizona Supreme Court, requesting review of the disallowance of $215 million of Four Corners SCR plant investments and deferrals (see “Four Corners SCR Cost Recovery” below for additional information) and the 20 basis point penalty reduction to the return on equity. On February 8, 2022, the Arizona Supreme Court declined to accept jurisdiction on APS’s Petition for Special Action. APS cannot predict the outcome of this proceeding.

Consistent with the 2019 Rate Case decision, APS implemented the new rates effective as of December 1, 2021. On December 3, 2021, ACC Staff notified the ACC of a discrepancy between the written decision, which approved the change in time-of-use on-peak hours to 4 p.m. to 7 p.m., but did not explicitly approve the 10-months contemplated in APS’s verbal testimony to implement the new time-of-use hours. On December 16, 2021, the ACC ordered APS to complete the implementation of the time-of-use peak period by April 1, 2022. On January 12, 2022, the ACC voted to extend until September 1, 2022, the deadline to complete the implementation of the new on-peak hours for residential customers. In addition, the ACC ordered extensive compliance and reporting obligations and will be continuing to explore whether penalties or rebates would be owed to certain customers. APS cannot predict the outcome of this matter.

APS expects to file an application with the ACC for its next general retail rate case by mid-year 2022 but is continuing to evaluate the timing of such filing.

See Note 4 for information regarding additional regulatory matters.

Four Corners SCR Cost Recovery

As part of APS’s 2019 Rate Case, APS included recovery of the deferral and rate base effects of the Four Corners SCR project. On November 2, 2021, the 2019 Rate Case decision was approved by the ACC allowing approximately $194 million of SCR related plant investments and cost deferrals in rate base and to recover, depreciate and amortize in rates based on an end-of-life assumption of July 2031. The decision also included a partial and combined disallowance of $215.5 million on the SCR investments and deferrals. APS believes the SCR plant investments and related SCR cost deferrals were prudently incurred, and on December 17, 2021, APS filed its Notice of Direct Appeal at the Arizona Court of Appeals requesting review of the $215.5 million disallowance. Based on the partial recovery of these investments and cost deferrals in current rates and the uncertainty of the outcome of the legal appeals process, APS has not recorded an impairment or write-off relating to the SCR plant investments or deferrals as of December 31, 2021. If the 2019 Rate Case decision to disallow $215.5 million of the SCRs is ultimately upheld, APS will be required to record a charge to its results of operations, net of tax, of approximately $154.4 million. We cannot predict the outcome of the legal challenges nor the timing of when this matter will be resolved. See Note 4 for additional information regarding the Four Corners SCR cost recovery.

68

Table of Contents

Financial Strength and Flexibility

Pinnacle West and APS currently have ample borrowing capacity under their respective credit facilities and may readily access these facilities ensuring adequate liquidity for each company.  Capital expenditures will be funded with internally generated cash and external financings, which may include issuances of long-term debt and Pinnacle West common stock.

Other Subsidiaries

Bright Canyon Energy. On July 31, 2014, Pinnacle West announced its creation of a wholly-owned subsidiary, BCE.  BCE’s strategy is to develop, own, operate and acquire energy infrastructure in a manner that leverages the Company’s core expertise in the electric energy industry.  In 2014, BCE formed a 50/50 joint venture with BHE U.S. Transmission LLC, a subsidiary of Berkshire Hathaway Energy Company.  The joint venture, named TransCanyon, is pursuing independent electric transmission opportunities within the 11 states that comprise the Western Electricity Coordinating Council, excluding opportunities related to transmission service that would otherwise be provided under the tariffs of the retail service territories of the venture partners’ utility affiliates.

On December 20, 2019, BCE acquired minority ownership positions in two wind farms under development by Tenaska Energy, Inc. and Tenaska Energy Holdings, LLC, the 242 MW Clear Creek and the 250 MW Nobles 2 wind farms. Clear Creek achieved commercial operation in May 2020 and Nobles 2 achieved commercial operation in December 2020. Both wind farms deliver power under long-term PPAs. BCE indirectly owns 9.9% of Clear Creek and 5.1% of Nobles 2.

El Dorado. El Dorado is a wholly-owned subsidiary of Pinnacle West. El Dorado owns debt investments and minority interests in several energy-related investments and Arizona community-based ventures. El Dorado committed to a $25 million investment in the Energy Impact Partners fund, which is an organization that focuses on fostering innovation and supporting the transformation of the utility industry. The investment will be made by El Dorado as investments are selected by the Energy Impact Partners fund. As of December 31, 2021, El Dorado has contributed approximately $10 million to the Energy Impact Partners fund. Additionally, El Dorado committed to a $25 million investment in invisionAZ Fund, which is a fund focused on analyzing, investing, managing, and otherwise dealing with investments in privately held early stage and emerging growth technology companies and businesses primarily based in the State of Arizona, or based in other jurisdictions and having existing or potential strategic or economic ties to companies or other interests in the State of Arizona.

Key Financial Drivers

In addition to the continuing impact of the matters described above, many factors influence our financial results and our future financial outlook, including those listed below.  We closely monitor these factors to plan for the Company’s current needs, and to adjust our expectations, financial budgets, and forecasts appropriately.

Electric Operating Revenues.  For the years 2019 through 2021, retail electric revenues comprised approximately 94% of our total operating revenues.  Our electric operating revenues are affected by customer growth or decline, variations in weather from period to period, customer mix, average usage per customer and the impacts of energy efficiency programs, distributed energy additions, electricity rates and tariffs, the recovery of PSA deferrals and the operation of other recovery mechanisms.  These revenue

69

Table of Contents

transactions are affected by the availability of excess generation or other energy resources and wholesale market conditions, including competition, demand, and prices.

Actual and Projected Customer and Sales Growth. Retail customers in APS’s service territory increased 2.2% for the year ended December 31, 2021, compared with the prior-year period. For the three years through 2021, APS’s customer growth averaged 2.2% per year. We currently project annual customer growth to be 1.5% to 2.5% for 2022, and the average annual growth will be in the range of 1.5% to 2.5% through 2024 based on anticipated steady population growth in Arizona during that period.

Retail electricity sales in kWh, adjusted to exclude the effects of weather variations, for the year ended December 31, 2021, compared with the prior-year period increased 4.2%, which reflects a correction to 2020 commercial and industrial customer sales volumes of 111 GWh (“2020 Sales Volume Correction.”). The 2020 Sales Volume Correction impacted prior disclosure in our Quarterly Reports on Form 10-Q. The retail electricity sales in kWh, adjusted to exclude the effects of weather variations, for the three-month period ended March 31, 2021, the six-month period ended June 30, 2021, and the nine-month period ended Sept 30, 2021 with the 2020 Sales Volume Correction reflected would have been 0.2%, 3.1% and 3.5%, respectively. While steady customer growth was offset by energy savings driven by customer conservation, energy efficiency, and distributed renewable generation initiatives, the main drivers of positive sales for this period were residential sales being stronger than anticipated due to continued work-from-home policies, a strong improvement in sales to commercial and industrial customers, and the ramp-up of new data center customers. Though the total expected impact of COVID-19 on future sales is currently unknown, APS experienced higher electric residential sales and lower electric commercial and industrial sales from the outset of the pandemic through April 2021. Beginning in May 2021, electric sales to commercial and industrial customers increased to levels in line with pre-COVID sales.

For the three years through 2021, annual retail electricity sales growth averaged 1.7%, adjusted to exclude the effects of weather variations. We currently project that annual retail electricity sales in kWh will increase in the range of 1.5% to 2.5% for 2022, and average annual growth will be in the range of 3.5% to 4.5% through 2024, including the effects of customer conservation, energy efficiency and distributed renewable generation initiatives, but excluding the effects of weather variations. This projected sales growth range includes the impacts of new, large manufacturing facilities, which are expected to contribute to average annual growth in the range of 1.0% to 2.0% through 2024. This projected sales growth range also includes our estimated contributions of several large data centers, but not all, and we will continue to estimate contributions and evaluate sales guidance as these customers develop more usage history. These estimates could be further impacted by slower than expected growth of the Arizona economy, slower than expected ramp-up of the new data centers, larger manufacturing facilities not coming to Arizona as expected, a shift away from remote work, slower than expected commercial and industrial expansions, or acceleration of the expected effects of customer conservation, energy efficiency and distributed renewable generation initiatives.

Consistent with our focus on continuously looking for improvement in our processes and procedures, we updated our weather normalization methodology in 2020 to better leverage available AMI data (smart meter data). While the prior method only used one to two months of daily usage data to estimate weather impacts, the new method utilizes a rolling four-year period of daily usage data, which improves the accuracy of estimated weather impacts on energy sales since many more data points are used for each calculation. The impact to our 2019-2021 average normalized sales growth from this change in methodology is 0.1%.

70

Table of Contents

Actual sales growth, excluding weather-related variations, may differ from our projections as a result of numerous factors, such as economic conditions, customer growth, usage patterns and energy conservation, ramp-up of data centers, impacts of energy efficiency programs and growth in DG, and responses to retail price changes.  Based on past experience, a 1% variation in our annual residential and small commercial and industrial kWh sales projections under normal business conditions can result in increases or decreases in annual net income of approximately $20 million, and a 1% variation in our annual large commercial and industrial kWh sales projections under normal business conditions can result in increases or decreases in annual net income of approximately $5 million.

Weather.  In forecasting the retail sales growth numbers provided above, we assume normal weather patterns based on historical data.  Historically, extreme weather variations have resulted in annual variations in net income in excess of $25 million.  However, our experience indicates that the more typical variations from normal weather can result in increases or decreases in annual net income of up to $15 million.

Fuel and Purchased Power Costs.  Fuel and purchased power costs included on our Consolidated Statements of Income are impacted by our electricity sales volumes, existing contracts for purchased power and generation fuel, our power plant performance, transmission availability or constraints, prevailing market prices, new generating plants being placed in service in our market areas, changes in our generation resource allocation, our hedging program for managing such costs and PSA deferrals and the related amortization.

Operations and Maintenance Expenses.  Operations and maintenance expenses are impacted by customer and sales growth, power plant operations, maintenance of utility plant (including generation, transmission, and distribution facilities), inflation, unplanned outages, planned outages (typically scheduled in the spring and fall), renewable energy and DSM related expenses (which are offset by the same amount of operating revenues) and other factors.

Depreciation and Amortization Expenses.  Depreciation and amortization expenses are impacted by net additions to utility plant and other property (such as new generation, transmission, and distribution facilities), and changes in depreciation and amortization rates.  See “Liquidity and Capital Resources” below for information regarding the planned additions to our facilities.

Pension and Other Postretirement Non-Service Credits, Net.  Pension and other postretirement non-service credits can be impacted by changes in our actuarial assumptions. The most relevant actuarial assumptions are the discount rate used to measure our net periodic costs/credit, the expected long-term rate of return on plan assets used to estimate earnings on invested funds over the long-term, the mortality assumptions and the assumed healthcare cost trend rates. We review these assumptions on an annual basis and adjust them as necessary.

Property Taxes.  Taxes other than income taxes consist primarily of property taxes, which are affected by the value of property in-service and under construction, assessment ratios, and tax rates.  The average property tax rate in Arizona for APS, which owns essentially all of our property, was 10.7% of the assessed value for 2021, 10.8% for 2020 and 10.9% for 2019. We expect property taxes to increase as we add new generating units and continue with improvements and expansions to our existing generating units and transmission and distribution facilities.

71

Table of Contents

Income Taxes.  Income taxes are affected by the amount of pretax book income, income tax rates, certain deductions, and non-taxable items, such as AFUDC.  In addition, income taxes may also be affected by the settlement of issues with taxing authorities. On December 22, 2017, the Tax Cuts and Jobs Act (the “Tax Act”) was enacted and was generally effective on January 1, 2018. Changes impacting the Company include a reduction in the corporate tax rate to 21%, revisions to the rules related to tax bonus depreciation, limitations on interest deductibility and an associated exception for certain public utilities, and requirements that certain excess deferred tax amounts of regulated utilities be normalized. See Note 5 for details of the impacts on the Company as of December 31, 2021. In APS’s 2017 Rate Case Decision, the ACC approved the TEAM, which was being used to pass through the income tax effects to retail customers of the Tax Act. As part of the 2019 Rate Case (defined above), all impacts of the Tax Act were removed from the TEAM and incorporated into APS's base rates. The TEAM was retained to address potential changes in tax law that may be enacted prior to a decision in APS’s next rate case. See Note 4 for details of the TEAM.

Interest Expense.  Interest expense is affected by the amount of debt outstanding and the interest rates on that debt. See Note 7 for further details.  The primary factors affecting borrowing levels are expected to be our capital expenditures, long-term debt maturities, equity issuances and internally generated cash flow.  An allowance for borrowed funds used during construction offsets a portion of interest expense while capital projects are under construction.  We stop accruing AFUDC on a project when it is placed in commercial operation.

RESULTS OF OPERATIONS

Pinnacle West’s only reportable business segment is our regulated electricity segment, which consists of traditional regulated retail and wholesale electricity businesses (primarily sales supplied under traditional cost-based rate regulation) and related activities and includes electricity generation, transmission, and distribution.

Operating Results – 2021 compared with 2020

Our consolidated net income attributable to common shareholders for the year ended December 31, 2021, was $619 million, compared with $551 million for the prior year.  The results reflect an increase of approximately $69 million for the regulated electricity segment primarily due to higher revenue driven by higher customer usage and growth, lower refunds in the current year related to the Tax Act, higher transmission revenues, the one-time charge in 2020 related to the Arizona Attorney General Matter, higher pension and other postretirement non-service credits, and lower other expenses, partially offset by the effects of weather, higher depreciation and amortization expense and higher income taxes, including lower amortization of excess deferred taxes.

72

Table of Contents

The following table presents net income attributable to common shareholders by business segment compared with the prior year:

Year Ended December 31,
20212020Net change
(dollars in millions)
Regulated Electricity Segment:
Operating revenues less fuel and purchased power expenses$2,645$2,589$56
Operations and maintenance(951)(953)2
Depreciation and amortization(651)(614)(37)
Taxes other than income taxes(235)(225)(10)
Pension and other postretirement non-service credits — net1135657
All other income and expenses, net612635
Interest charges, net of allowance for borrowed funds used during construction(233)(229)(4)
Income taxes (Note 5)(110)(78)(32)
Less income related to noncontrolling interests (Note 18)(17)(19)2
Regulated electricity segment income62255369
All other(3)(2)(1)
Net Income Attributable to Common Shareholders$619$551$68

Operating revenues less fuel and purchased power expenses.  Regulated electricity segment operating revenues less fuel and purchased power expenses were $56 million higher for the year ended December 31, 2021, compared with the prior year.  The following table summarizes the major components of this change:

Increase (Decrease)
Operating revenuesFuel and purchased power expensesNet change
(dollars in millions)
Higher retail revenue due to changes in customer usage patterns and customer growth, partially offset by the impacts of energy efficiency and distributed generation$112$36$76
Lower refunds in the current year related to the Tax Act (Note 4)3030
Higher transmission revenues (Note 4)2626
Arizona Attorney General Matter (Note 11)2424
Higher renewable energy regulatory surcharges, offset by operations and maintenance costs14(5)19
Changes in net fuel and purchased power costs, including off-system sales margins and related deferrals158160(2)
Effects of weather(150)(36)(114)
Miscellaneous items, net14(3)
Total$215$159$56

73

Table of Contents

Operations and maintenance.  Operations and maintenance expenses decreased $2 million for the year ended December 31, 2021, compared with the prior-year period primarily because of:

•A decrease of $21 million primarily related to the COVID Customer Support Fund (see Note 4), personal protective equipment and other health and safety-related costs for COVID-19 response;

•A decrease of $13 million for costs related to transmission and distribution;

•An increase of $16 million primarily related to costs for renewable energy and similar regulatory programs, which are partially offset in operating revenues and purchased power;

•An increase of $12 million related to employee benefits; and

•An increase of $4 million for corporate resources and other miscellaneous factors.

Depreciation and amortization.  Depreciation and amortization expenses were $37 million higher for the year ended December 31, 2021, compared with the prior-year period primarily due to increased plant in service of $31 million and the regulatory deferrals for the Ocotillo modernization project and the Four Corners SCR project of $6 million.

Taxes other than income taxes.  Taxes other than income taxes were $10 million higher for the year ended December 31, 2021, compared with the prior-year period primarily due to higher property values.

Pension and other postretirement non-service credits, net. Pension and other postretirement non-service credits, net were $57 million higher for the year ended December 31, 2021, compared to the prior-year period primarily due to actual market returns exceeding estimated returns in 2020.

All other income and expenses, net. All other income and expenses, net were $35 million higher for the year ended December 31, 2021, compared to the prior-year period primarily due to the prior year CCT and APS Foundation contributions.

Interest charges, net of allowance for borrowed funds used during construction. Interest charges, net of allowance for borrowed funds used during construction were $4 million higher for the year ended December 31, 2021, compared to the prior-year period primarily due to higher debt balances in the current period, partially offset by higher allowance for borrowed funds due to increased capital expenditures.

Income taxes.  Income taxes were $32 million higher for the year ended December 31, 2021, compared with the prior-year period primarily due to higher pre-tax net income and lower amortization of excess deferred taxes, partially offset by a net operating loss carryback benefit that the Company recognized during the first quarter of 2021.

74

Table of Contents

LIQUIDITY AND CAPITAL RESOURCES

Overview

Pinnacle West’s primary cash needs are for dividends to our shareholders and principal and interest payments on our indebtedness.  The level of our common stock dividends and future dividend growth will be dependent on declaration by our Board of Directors and based on a number of factors, including our financial condition, payout ratio, free cash flow and other factors.

Our primary sources of cash are dividends from APS and external debt and equity issuances.  An ACC order requires APS to maintain a common equity ratio of at least 40%.  As defined in the related ACC order, the common equity ratio is defined as total shareholder equity divided by the sum of total shareholder equity and long-term debt, including current maturities of long-term debt.  At December 31, 2021, APS’s common equity ratio, as defined, was 51%.  Its total shareholder equity was approximately $6.6 billion, and total capitalization was approximately $13.1 billion.  Under this order, APS would be prohibited from paying dividends if such payment would reduce its total shareholder equity below approximately $5.2 billion, assuming APS’s total capitalization remains the same.  This restriction does not materially affect Pinnacle West’s ability to meet its ongoing cash needs or ability to pay dividends to shareholders.

APS’s capital requirements consist primarily of capital expenditures and maturities of long-term debt.  APS funds its capital requirements with cash from operations and, to the extent necessary, external debt financings and equity infusions from Pinnacle West.

Summary of Cash Flows

The following tables present net cash provided by (used for) operating, investing, and financing activities for the years ended December 31, 2021, and 2020 (dollars in millions):

Pinnacle West Consolidated

20212020
Net cash flow provided by operating activities$860$967
Net cash flow used for investing activities(1,387)(1,278)
Net cash flow provided by financing activities477361
Net increase (decrease) in cash and cash equivalents$(50)$50

Arizona Public Service Company

20212020
Net cash flow provided by operating activities$865$929
Net cash flow used for investing activities(1,391)(1,286)
Net cash flow provided by financing activities478404
Net increase (decrease) in cash and cash equivalents$(48)$47

75

Table of Contents

Operating Cash Flows

2021 Compared with 2020. Pinnacle West’s consolidated net cash provided by operating activities was $860 million in 2021 compared to $967 million in 2020, a decrease of $107 million in net cash provided primarily due to $252 million higher fuel and purchased power costs, $93 million higher payments for operations and maintenance costs, $15 million higher other taxes and $11 million higher interest payments, partially offset by $175 million higher cash receipts from electric revenues and $93 million other changes in working capital. The difference between APS and Pinnacle West’s net cash provided by operating activities primarily relates to APS’s income tax cash payments to Pinnacle West and other changes in working capital.

Retirement plans and other postretirement benefits. Pinnacle West sponsors a qualified defined benefit pension plan and a non-qualified supplemental excess benefit retirement plan for the employees of Pinnacle West and our subsidiaries. Pinnacle West also sponsors other postretirement benefit plans for the employees of Pinnacle West and its subsidiaries. The requirements of the Employee Retirement Income Security Act of 1974 (“ERISA”) require us to contribute a minimum amount to the qualified plan.  We contribute at least the minimum amount required under ERISA regulations, but no more than the maximum tax-deductible amount.  The minimum required funding takes into consideration the value of plan assets and our pension benefit obligations.  Under ERISA, the qualified pension plan was estimated to be 138% funded as of January 1, 2022, and was 131% as of January 1, 2021. Future year contribution amounts are dependent on plan asset performance and plan actuarial assumptions.  We made contributions to our pension plan totaling $100 million in 2021, $100 million in 2020, and $150 million in 2019.  The minimum required contributions for the pension plan are zero for the next three years and we do not expect to make any voluntary contributions in 2022, 2023 or 2024. Regarding contributions to our other postretirement benefit plan, we did not make any contributions in 2021 or 2020 and do not expect to make any contributions in 2022, 2023 or 2024. The Company was reimbursed $24 million in 2021, $26 million in 2020, and $30 million in 2019 for prior years retiree medical claims from the other postretirement benefit plan trust assets. We continually monitor financial market volatility and its impact on our retirement plans and other postretirement benefits, but we believe, our liability driven investment strategy helps to minimize the impact of market volatility on our plan’s funded status. For instance, our pension plan’s funded status, as measured for accounting principles generally accepted in the United States of America (“GAAP”) purposes, is still above 107% funded as of December 31, 2021, and our postretirement benefit plans have a funded status, also as measured for GAAP purposes at December 31, 2021, in excess of 145%. See Note 8 for additional details.

The Coronavirus Aid, Relief, and Economic Security (CARES) Act allows employers to defer payments of the employer share of Social Security payroll taxes that would have otherwise been owed from March 27, 2020, through December 31, 2020. We deferred the cash payment of the employer’s portion of Social Security payroll taxes for the period July 1, 2020, through December 31, 2020 that was approximately $18 million. We paid approximately $9 million on December 28, 2021, and will pay the second half of this cash deferral by December 31, 2022.

Investing Cash Flows

2021 Compared with 2020. Pinnacle West’s consolidated net cash used for investing activities was $1,387 million in 2021 compared to $1,278 million in 2020, an increase of $109 million in net cash used primarily related to increased capital expenditures.

76

Table of Contents

Capital Expenditures.  The following table summarizes the estimated capital expenditures for the next three years:

Capital Expenditures

(dollars in millions)

Estimated for the Year Ended December 31,
202220232024
APS
Generation:
Clean:
Nuclear Generation$110$120$110
Renewables and Energy Storage Systems (“ESS”) (a)230210450
Other Generation (b)250270190
Distribution510530500
Transmission250210210
Other (c)175185190
Total APS$1,525$1,525$1,650

(a)APS Solar Communities program, energy storage, renewable projects, and other clean energy projects.

(b)Includes generation environmental projects.

(c)Primarily information systems and facilities projects.

The table above does not include capital expenditures related to BCE projects.

Generation capital expenditures are comprised of various additions and improvements to APS’s clean resources, including nuclear plants, renewables and ESS. Generation capital expenditures also include improvements to existing fossil plants. Examples of the types of projects included in the forecast of generation capital expenditures are additions of renewables and energy storage, and upgrades and capital replacements of various nuclear and fossil power plant equipment, such as turbines, boilers, and environmental equipment.  We are monitoring the status of environmental matters, which, depending on their final outcome, could require modification to our planned environmental expenditures.

Distribution and transmission capital expenditures are comprised of infrastructure additions and upgrades, capital replacements, and new customer construction.  Examples of the types of projects included in the forecast include power lines, substations, and line extensions to new residential and commercial developments.

Capital expenditures will be funded with internally generated cash and external financings, which may include issuances of long-term debt and Pinnacle West common stock.

Financing Cash Flows and Liquidity

2021 Compared with 2020. Pinnacle West’s consolidated net cash provided by financing activities was $477 million in 2021 compared to $361 million of net cash provided in 2020, an increase of $116 million in net cash provided by financing activities primarily due to $915 million lower long-term debt

77

Table of Contents

repayments, partially offset by $850 million in lower issuances of long-term debt, a net increase in short-term borrowings of $69 million and higher dividend payments of $19 million.

APS’s consolidated net cash provided by financing activities was $478 million in 2021 compared to $404 million in 2020, an increase of $74 million in net cash provided by financing activities primarily due to $465 million lower long-term debt repayments, offset by $653 million in lower issuances of long-term debt, a net increase in short-term borrowings of $279 million, and higher dividend payments of $19 million.

Significant Financing Activities.  On December 15, 2021, the Pinnacle West Board of Directors declared a dividend of $0.85 per share of common stock, payable on March 1, 2022, to shareholders of record on February 1, 2022. During 2021, Pinnacle West increased its indicated annual dividend from $3.32 per share to $3.40 per share. For the year ended December 31, 2021, Pinnacle West’s total dividends paid per share of common stock were $3.34 per share, which resulted in dividend payments of $369 million.

Available Credit Facilities.  Pinnacle West and APS maintain committed revolving credit facilities in order to enhance liquidity and provide credit support for their commercial paper. See Note 6 for more information on available credit facilities.

Other Financing Matters.  See Note 16 for information related to the change in our margin and collateral accounts.

Debt Provisions

Pinnacle West’s and APS’s debt covenants related to their respective bank financing arrangements include maximum debt to capitalization ratios.  Pinnacle West and APS comply with these covenants.  For both Pinnacle West and APS, these covenants require that the ratio of consolidated debt to total consolidated capitalization not exceed 65%.  At December 31, 2021, the ratio was approximately 56% for Pinnacle West and 50% for APS.  Failure to comply with such covenant levels would result in an event of default which, generally speaking, would require the immediate repayment of the debt subject to the covenants and could “cross-default” other debt.  See further discussion of “cross-default” provisions below.

Neither Pinnacle West’s nor APS’s financing agreements contain “rating triggers” that would result in an acceleration of the required interest and principal payments in the event of a rating downgrade.  However, our bank credit agreements contain a pricing grid in which the interest rates we pay for borrowings thereunder are determined by our current credit ratings.

All of Pinnacle West’s loan agreements contain “cross-default” provisions that would result in defaults and the potential acceleration of payment under these loan agreements if Pinnacle West or APS were to default under certain other material agreements.  All of APS’s bank agreements contain “cross-default” provisions that would result in defaults and the potential acceleration of payment under these bank agreements if APS were to default under certain other material agreements.  Pinnacle West and APS do not have a material adverse change restriction for credit facility borrowings.

On December 17, 2020, the ACC issued a financing order that, subject to specified parameters and procedures, increased APS’s long-term debt limit from $5.9 billion to $7.5 billion, and authorized APS’s short-term debt authorization equal to the sum of (i) 7% of APS’s capitalization, and (ii) $500

78

Table of Contents

million (which is required to be used for costs relating to purchases of natural gas and power). See Note 7 for further discussions of liquidity matters.

Credit Ratings

The ratings of securities of Pinnacle West and APS as of February 17, 2022, are shown below. We are disclosing these credit ratings to enhance understanding of our cost of short-term and long-term capital and our ability to access the markets for liquidity and long-term debt. The ratings reflect the respective views of the rating agencies, from which an explanation of the significance of their ratings may be obtained. There is no assurance that these ratings will continue for any given period of time. The ratings may be revised or withdrawn entirely by the rating agencies if, in their respective judgments, circumstances so warrant. Any downward revision or withdrawal may adversely affect the market price of Pinnacle West’s or APS’s securities and/or result in an increase in the cost of, or limit access to, capital. Such revisions may also result in substantial additional cash or other collateral requirements related to certain derivative instruments, insurance policies, natural gas transportation, fuel supply, and other energy-related contracts. On October 12, 2021, Fitch Ratings downgraded the issuer ratings of the Company and APS from A- to BBB+ and the senior unsecured ratings of the Company and APS from A- and A to BBB+ and A-, respectively, with a negative outlook retained. Fitch Ratings also affirmed the commercial paper ratings of the Company and APS at F2. On November 9, 2021, S&P downgraded the issuer ratings of the Company and APS from A- to BBB+. S&P also downgraded the senior unsecured ratings of the Company and APS from BBB+ to BBB and A- to BBB+, respectively, with a negative outlook retained. Commercial paper ratings remained unchanged at A-2 for both entities. On November 17, 2021, Moody’s downgraded both the issuer and senior unsecured ratings of the Company from A3 to Baa1. Concurrently, Moody’s downgraded the issuer and senior unsecured ratings of APS from A2 to A3. Commercial paper for APS was downgraded from P-1 to P-2. The commercial paper ratings for the Company remain unchanged. The outlooks for both companies are negative. At this time, we believe we have sufficient available liquidity resources to respond to a downward revision to our credit ratings.

Moody’sStandard & Poor’sFitch
Pinnacle West
Corporate credit ratingBaa1BBB+BBB+
Senior unsecuredBaa1BBBBBB+
Commercial paperP-2A-2F2
OutlookNegativeNegativeNegative
APS
Corporate credit ratingA3BBB+BBB+
Senior unsecuredA3BBB+A-
Commercial paperP-2A-2F2
OutlookNegativeNegativeNegative

79

Table of Contents

Contractual Obligations

Pinnacle West has contractual obligations and other commitments that will need to be funded in the future, in addition to its capital expenditure programs. Material contractual obligations and other commitments are as follows:

•Pinnacle West and APS have material long-term debt obligations that mature at various dates through 2050 and bear interest principally at fixed rates. Interest on variable-rate long-term debt is determined by using average rates at December 31, 2021. See Note 7.

•Pinnacle West and APS maintain committed revolving credit facilities. See Note 6 for short-term debt details.

•Fuel and purchased power commitments include purchases of coal, electricity, natural gas, renewable energy, nuclear fuel, and natural gas transportation. See Notes 4 and 11. Purchase obligations includes capital expenditures and other obligations. See Note 11. Commitments related to purchased power lease contracts are also considered fuel and purchased power commitments. See Note 9.

•APS holds certain contracts to purchase renewable energy credits in compliance with the RES. See Notes 4 and 11.

•APS must reimburse certain coal providers for amounts incurred for final and contemporaneous coal mine reclamation. See Note 11.

•APS is required to make payments to the noncontrolling interests related to the Palo Verde sale leaseback through 2033. See Note 18.

CRITICAL ACCOUNTING POLICIES

In preparing the financial statements in accordance with GAAP, management must often make estimates and assumptions that affect the reported amounts of assets, liabilities, revenues, expenses, and related disclosures at the date of the financial statements and during the reporting period.  Some of those judgments can be subjective and complex, and actual results could differ from those estimates.  We consider the following accounting policies to be our most critical because of the uncertainties, judgments and complexities of the underlying accounting standards and operations involved.

Regulatory Accounting

Regulatory accounting allows for the actions of regulators, such as the ACC and FERC, to be reflected in our financial statements.  Their actions may cause us to capitalize costs that would otherwise be included as an expense in the current period by unregulated companies.  Regulatory assets represent incurred costs that have been deferred because they are probable of future recovery in customer rates.  Regulatory liabilities generally represent amounts collected in rates to recover costs expected to be incurred in the future or amounts collected in excess of costs incurred and are refundable to customers. Management judgments include continually assessing the likelihood of future recovery of regulatory assets and/or a disallowance of part of the cost of recently completed plant, by considering factors such as applicable regulatory environment changes and recent rate orders to other regulated entities in the same jurisdiction.  This determination reflects the current political and regulatory climate in Arizona and is

80

Table of Contents

subject to change in the future.  If future recovery of costs ceases to be probable, the assets would be written off as a charge in current period earnings, except for pension benefits, which would be charged to OCI and result in lower future earnings.  Management judgments also include assessing the impact of potential ACC or FERC Commission-ordered refunds to customers on regulatory liabilities. We had $1,712 million of regulatory assets and $2,795 million of regulatory liabilities on the Consolidated Balance Sheets at December 31, 2021. See Notes 1 and 4 for more information.

Pensions and Other Postretirement Benefit Accounting

Changes in our actuarial assumptions used in calculating our pension and other postretirement benefit assets, liabilities and expense can have a significant impact on our earnings and financial position.  The most relevant actuarial assumptions are the discount rate used to measure our liability and net periodic cost, the expected long-term rate of return on plan assets used to estimate earnings on invested funds over the long-term, the mortality assumptions, and the assumed healthcare cost trend rates.  We review these assumptions on an annual basis and adjust them as necessary.

The following chart reflects the sensitivities that a change in certain actuarial assumptions would have had on the December 31, 2021, reported pension assets and liabilities on the Consolidated Balance Sheets and our 2021 reported pension expense, after consideration of amounts capitalized or billed to electric plant participants, on Pinnacle West’s Consolidated Statements of Income (dollars in millions):

Increase (Decrease)
Actuarial Assumption (a)Impact on Pension PlansImpact on Pension Expense
Discount rate:
Increase 1%$(388)$5
Decrease 1%47115
Expected long-term rate of return on plan assets:
Increase 1%(28)
Decrease 1%28

(a)Each fluctuation assumes that the other assumptions of the calculation are held constant while the rates are changed by one percentage point.

81

Table of Contents

The following chart reflects the sensitivities that a change in certain actuarial assumptions would have had on the December 31, 2021, other postretirement benefit obligation and our 2021 reported other postretirement benefit expense, after consideration of amounts capitalized or billed to electric plant participants, on Pinnacle West’s Consolidated Statements of Income (dollars in millions):

Increase (Decrease)
Actuarial Assumption (a)Impact on Other Postretirement Benefit PlansImpact on Other Postretirement Benefit Expense
Discount rate:
Increase 1%$(72)$(4)
Decrease 1%905
Healthcare cost trend rate (b):
Increase 1%808
Decrease 1%(65)(7)
Expected long-term rate of return on plan assets – pretax:
Increase 1%(6)
Decrease 1%6

(a)Each fluctuation assumes that the other assumptions of the calculation are held constant while the rates are changed by one percentage point.

(b)This assumes a 1% change in the initial and ultimate healthcare cost trend rate.

See Note 8 for further details about our pension and other postretirement benefit plans.

Fair Value Measurements

We account for derivative instruments, investments held in our nuclear decommissioning trusts fund, investments held in our other special use funds, certain cash equivalents, and plan assets held in our retirement and other benefit plans at fair value on a recurring basis.  Fair value is the price that would be received to sell an asset or paid to transfer a liability in an orderly transaction between market participants at the measurement date.  We use inputs, or assumptions that market participants would use, to determine fair market value. We utilize valuation techniques that maximize the use of observable inputs and minimize the use of unobservable inputs.  The significance of a particular input determines how the instrument is classified in a fair value hierarchy.  The determination of fair value sometimes requires subjective and complex judgment.  Our assessment of the inputs and the significance of a particular input to fair value measurement may affect the valuation of the instruments and their placement within a fair value hierarchy.  Actual results could differ from our estimates of fair value.  See Note 1 for a discussion of accounting policies and Note 13 for fair value measurement disclosures.

Asset Retirement Obligations

We recognize an ARO for the future decommissioning or retirement of our tangible long-lived assets for which a legal obligation exists. The ARO liability represents an estimate of the fair value of the current obligation related to decommissioning and the retirement of those assets. ARO measurements inherently involve uncertainty in the amount and timing of settlement of the liability. We use an expected cash flow approach to measure the amount we recognize as an ARO. This approach applies probability weighting to discounted future cash flow scenarios that reflect a range of possible outcomes. The scenarios

82

Table of Contents

consider settlement of the ARO at the expiration of the asset’s current license or lease term and expected decommissioning dates. The fair value of an ARO is recognized in the period in which it is incurred. The associated asset retirement costs are capitalized as part of the carrying value of the long-lived asset and are depreciated over the life of the related assets. In addition, we accrete the ARO liability to reflect the passage of time. Changes in these estimates and assumptions could materially affect the amount of the recorded ARO for these assets. In accordance with GAAP accounting, APS accrues removal costs for its regulated utility assets, even if there is no legal obligation for removal.

AROs as of December 31, 2021 are described further in Note 12.

OTHER ACCOUNTING MATTERS

In July 2021, a new accounting standard, ASU 2021-05, was issued that amends lessor’s accounting treatment for certain lease transactions with variable lease payments. We adopted the standard on January 1, 2022 using a prospective approach. The adoption of this standard did not impact our financial statements. See Note 3 for additional information.

MARKET AND CREDIT RISKS

Market Risks

Our operations include managing market risks related to changes in interest rates, commodity prices, investments held by our nuclear decommissioning trust, other special use funds and benefit plan assets.

Interest Rate and Equity Risk

We have exposure to changing interest rates.  Changing interest rates will affect interest paid on variable-rate debt and the market value of fixed income securities held by our nuclear decommissioning trust, other special use funds (see Note 13 and Note 19), and benefit plan assets.  The nuclear decommissioning trust, other special use funds and benefit plan assets also have risks associated with the changing market value of their equity and other non-fixed income investments.  Nuclear decommissioning and benefit plan costs are recovered in regulated electricity prices.

83

Table of Contents

The tables below present contractual balances of our consolidated long-term and short-term debt at the expected maturity dates, as well as the fair value of those instruments on December 31, 2021, and 2020.  The interest rates presented in the tables below represent the weighted-average interest rates as of December 31, 2021, and 2020 (dollars in millions):

Pinnacle West – Consolidated

Short-Term DebtVariable-Rate Long-Term DebtFixed-Rate Long-Term Debt
InterestInterestInterest
2021RatesAmountRatesAmountRatesAmount
20220.18%$2920.78%$150$
2023
20240.85%1503.35%250
20251.99%800
20262.55%250
Years thereafter0.22%363.87%5,480
Total$292$336$6,780
Fair value$292$336$7,390
Short-Term DebtVariable-Rate Long-Term DebtFixed-Rate Long-Term Debt
InterestInterestInterest
2020RatesAmountRatesAmountRatesAmount
20210.40%$169$$
2022
2023
20243.35%250
20251.99%800
Years thereafter0.18%363.95%5,280
Total$169$36$6,330
Fair value$169$36$7,577

84

Table of Contents

The tables below present contractual balances of APS’s long-term and short-term debt at the expected maturity dates, as well as the fair value of those instruments on December 31, 2021, and 2020.  The interest rates presented in the tables below represent the weighted-average interest rates as of December 31, 2021, and 2020 (dollars in millions):

APS — Consolidated

Short-Term DebtVariable-Rate Long-Term DebtFixed-Rate Long-Term Debt
InterestInterestInterest
2021RatesAmountRatesAmountRatesAmount
20220.18%$279$$
2023
20243.35%250
20253.15%300
20262.55%250
Years thereafter0.22%363.87%5,480
Total$279$36$6,280
Fair value$279$36$6,898
Variable-Rate Long-Term DebtFixed-Rate Long-Term Debt
InterestInterest
2020RatesAmountRatesAmount
2021$$
2022
2023
20243.35%250
20253.15%300
Years thereafter0.18%363.95%5,280
Total$36$5,830
Fair value$36$7,068

Commodity Price Risk

We are exposed to the impact of market fluctuations in the commodity price and transportation costs of electricity and natural gas.  Our risk management committee, consisting of officers and key management personnel, oversees company-wide energy risk management activities to ensure compliance with our stated energy risk management policies.  We manage risks associated with these market fluctuations by utilizing various commodity instruments that may qualify as derivatives, including futures, forwards, options, and swaps.  As part of our risk management program, we use such instruments to hedge purchases and sales of electricity and natural gas.  The changes in market value of such contracts have a high correlation to price changes in the hedged commodities.

85

Table of Contents

The following table shows the net pretax changes in mark-to-market of our derivative positions (dollars in millions):

December 31, 2021December 31, 2020
Mark-to-market of net positions at beginning of year$(13)$(71)
Increase in regulatory liability12057
Recognized in OCI:
Mark-to-market losses realized during the period1
Change in valuation techniques
Mark-to-market of net positions at end of year$107$(13)

The table below shows the fair value of maturities of our derivative contracts (dollars in millions) at December 31, 2021, by maturities and by the type of valuation that is performed to calculate the fair values, classified in their entirety based on the lowest level of input that is significant to the fair value measurement.  See Note 1, “Derivative Accounting” and “Fair Value Measurements,” for more discussion of our valuation methods.

Source of Fair Value20222023202420252026Total Fair Value
Observable prices provided by other external sources$63$35$12$$$110
Prices based on unobservable inputs(3)(3)
Total by maturity$60$35$12$$$107

The table below shows the impact that hypothetical price movements of 10% would have on the market value of our risk management assets and liabilities included on Pinnacle West’s Consolidated Balance Sheets (dollars in millions):

December 31, 2021 Gain (Loss)December 31, 2020 Gain (Loss)
Price Up 10%Price Down 10%Price Up 10%Price Down 10%
Mark-to-market changes reported in:
Regulatory asset (liability) (a)
Electricity$$$4$(4)
Natural gas50(50)49(49)
Total$50$(50)$53$(53)

(a)These contracts are economic hedges of our forecasted purchases of natural gas and electricity.  The impact of these hypothetical price movements would substantially offset the impact that these same price movements would have on the physical exposures being hedged.  To the extent the amounts are eligible for inclusion in the PSA, the amounts are recorded as either a regulatory asset or liability.

86

Table of Contents

Credit Risk

We are exposed to losses in the event of non-performance or non-payment by counterparties.  See Note 16 for a discussion of our credit valuation adjustment policy.